84 12. 8: Using Variance Analysis with Activity-Based Costing

  • CCBYNCSA
  • Last updated
    Dec 28, 2020
  • Anonymous
  • LibreTexts

 Learning Objectives 

  • Explain how to use cost variance analysis with activity-based costing.

Question: As discussed in Chapter 6, activity -based costing focuses on identifying activities required to make a product, forming cost pools for each activity, and allocating overhead costs to products based on the products’ use of each activity. Rather than establishing one standard variable overhead rate and standard quantity based on one cost driver,

activity -based costing establishes several standard variable overhead rates and quantities, each having its own cost driver. How would variance analysis be implemented for a company that uses activity -based costing?

Let’s work through an example of variance analysis using activity-based costing. Suppose Jerry’s Ice Cream identified three significant activities and established three standard rates to allocate variable manufacturing overhead instead of one rate based on direct labor hours. Information for the three activities for last year is:

Activity Standard Rate Standard Quantity per Unit Produced Actual Costs Actual Quantity
Purchase orders $25 per purchase order 0.01 orders per unit $42,000 1,600 purchase orders
Product testing $0.20 per test minute 1 minute per unit $31,000 180,000 test minutes
Energy $0.05 per minute of machine time 2 minutes per unit $27,000 575,000 minutes of machine time

Recall that Jerry’s produced 210,000 units for the year. Figure 12.11 shows the resulting variable overhead variance analysis. Notice that the format for Figure 12.11 is the same as for Figure 12.8. The variance calculations are also the same except variances are calculated for three activities rather than one. Note that total actual variable overhead costs remain at $100,000, but they are simply broken out into 3 activities ($100,000 = $42,000 for purchase orders + $31,000 for product testing + $27,000 for energy costs). Also, the flexible budget presented in Figure 12.11, totaling $115,500, differs from the flexible budget presented earlier since Jerry’s is using a different cost system in this example, which often results in different budgeted amounts ($115,500 = $52,500 purchase orders + $42,000 product testing + $21,000 energy).

Figure 10.11.png

Figure 12.11 : – Variable Overhead Variance Analysis for Jerry’s Ice Cream Using Activity-Based Costing

Note: AQ = Actual quantity of activity . SR = Standard variable manufacturing overhead rate per unit of activity . SQ = Standard quantity of activity given actual production of 210,000 units.

*Standard quantity of 2,100 purchase orders = Standard of 0.01 purchase orders per unit × 210,000 actual units produced.

**$2,000 unfavorable variable overhead spending variance = $42,000 −$40,000. Variance is unfavorable because the actual variable overhead cost is higher than the expected cost given actual quantity of 1,600 purchase orders.

† $(12,500) favorable variable overhead efficiency variance = $40,000 – $52,500. Variance is favorable because the 1,600 actual purchase orders are lower than the 2,100 expected (budgeted) purchase orders.

This type of costing system and resulting variance analysis provides management with further information regarding variable overhead costs and variances. As discussed earlier, management often establishes criteria to decide which variances to investigate. Assume that management of Jerry’s Ice Cream chooses to investigate the $7,750 unfavorable efficiency variance associated with energy. The management would like to know why 575,000 minutes of actual machine time were used instead of the expected 420,000 minutes. Perhaps the machines were operating poorly due to cutbacks in maintenance, or maybe new employees were not as efficient using the machines. Whatever the cause, Jerry’s has identified the issue by integrating its activity-based costing system with the cost variance analysis concepts discussed in this chapter.

 Key Takeaway 

Using cost variance analysis with activity-based costing is much like using cost variance analysis with traditional costing. Both utilize a spending variance and an efficiency variance. However, activity -based costing requires calculating a spending and efficiency variance for each activity rather than only one activity base typically used in traditional costing.

Review problem 12.7

Assume Carol’s Cookies uses activity -based costing to allocate variable manufacturing overhead costs instead of one rate based on direct labor hours. Carol identified three activities with the following information for last year.

Activity
Standard Rate Standard Quantity per Unit Produced Actual Costs Actual Quantity
Indirect materials $0.60 per pound 0.5 pounds per unit $130,000 220,000 pounds
Product testing $0.10 per test minute 2 minutes per unit $ 60,000 750,000 test minutes
Energy $0.12 per minute of machine time 4 minutes per unit $170,000 1,400,000 minutes of machine time

Recall that Carol’s Cookies produced and sold 390,000 units for the year. Prepare a variance analysis for Carol’s Cookies using the format shown in Figure 12.11.

Answer

License

Icon for the Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License

Cost Accounting Copyright © 2023 by William (Bill) Bonner is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License, except where otherwise noted.

Share This Book